10-07-22
The apparatus completed final assembly with release to testing. Once complete it will be released to quality followed by any graphics being applied before being made ready for final inspection.
09-09-22
The cab started initial assembly, the frame build continued, the pump house completed assembly and was staged. The body completed initial assembly and was staged.
09-02-22
The cab continued initial assembly, the frame build continued and the pump house continued assembly. The body continued paint and started initial assembly.
08-26-22
The cab completed paint and began initial assembly, the frame build continued, the pump house began assembly. The body completed fabrication and started the paint process.
08-19-22
The cab continued the paint process, the frame build began, and the body began fabrication.