05-05-23
The apparatus was completing final assembly and releasing to test. Once testing completes, the apparatus will release to quality and graphics where any remaining content will be applied. It will then be made ready for final inspection. This is the last scheduled report.
04-14-23
The cab was being installed on the frame, the pump house remained staged, and the body began initial assembly.
04-07-23
The cab completed initial assembly and was staged, the frame build continued, and the pump house and body remained staged.
03-31-23
The cab continued initial assembly, the frame build continued, the pump house remained staged, and the body was staged for initial assembly.
03-24-23
The cab continued initial assembly, the frame build continued, the pump house is staged, and the body completed the paint process.
03-17-23
The cab continued initial assembly, the frame build continued, the pump house completed initial assembly and was staged, and the body began the paint process.
03-10-23
The cab continued initial assembly, the frame build began, the pump house was painted and staged, and the body completed fabrication and was staged.
03-03-23
The cab completed paint and began initial assembly, the pump house began initial assembly, and the body began fabrication.
01-27-23
This Pierce apparatus is now in production. In this report, the cab began fabrication.