37457 – Howell – Enforcer 107′ Ascendant Aerial

Enforcer 107' Ascendant Aerial
Job #: 37457

PROGRESS UPDATES


06-02-23

In this report, the apparatus remained staged while the aerial device continued assembly.


05-12-23

In this report the body completed initial assembly and was merged with the chassis, followed by the start of final assembly.


05-05-23

The chassis continued assembly while the body began initial assembly.


04-29-23

The cab and pump house were installed on the frame while assembly continued, and the body was unavailable for photos


04-21-23

The cab completed initial assembly and was staged, the frame build continued, the pump house remained staged, and the body made progress through paint and was staged.


04-14-23

The cab continued initial assembly, the frame build continued, the pump house remained staged, and the body continued the paint process.


04-07-23

The cab started initial assembly, the frame build continued, the pump house completed initial assembly and is staged, and the body started the paint process.


03-31-23

The cab was staged, the frame build began, the pump house was painted, and the body remained staged.


03-24-23

The cab completed paint and was staged, the pump house began initial assembly, and the body released to paint.


03-17-23

The cab continued through paint while the body was fabricated and staged.


03-10-23

The cab began the paint process.