PROGRESS UPDATES


12-08-23

In this report, the apparatus completed testing and was released to quality and graphics.


12-01-23

In this report, the aerial device was pinned to the apparatus followed by the start of aerial testing.


11-17-23

In this report, the apparatus completed final assembly while the aerial device arrived and was staged.


11-10-23

In this report, final assembly continued.


10-27-23

In this report, the torque box was merged with the chassis while the front and rear body modules moved through initial assembly.


10-20-23

In this report, the cab and pump house were installed on the frame, the torque box continued assembly, the front body module remained staged, and the rear body module completed paint.


10-13-23

In this report the cab began initial assembly, the frame build
continued, the pump house remained staged, the torque box began
assembly, the front body module remained staged, and the rear
body module continued through paint.


10-07-23

In this report the cab was staged to begin initial assembly, the frame build continued, the pump house remained staged, the torque box was staged (no photos), the front body module remained staged, and the rear body module began the paint process.


09-29-23

In this report the cab was unavailable for photos, the frame build began, the pump house remained staged, the torque box was staged, and the front and rear body modules remained staged.


09-22-23

In this report the cab continued the paint process, the pump house completed initial assembly, and the front and rear body modules remained staged.


09-15-23

In this report the cab remained staged to continue through paint, the pump house continued initial assembly, the front body module was staged, and the rear body module remained staged.


09-08-23

In this report the cab was staged to continue through paint, the pump house remained staged to continue initial assembly, the front body module was painted, and the rear body module remained staged.


09-01-23

In this report, the cab continued the paint process, the pump house was staged to continue initial assembly, and the rear body module remained staged.