08-18-23
In this report, the apparatus completed final assembly and test and was released to quality and graphics, where any additional content will be installed. Once complete the apparatus will be made ready for the final inspection. This is the last scheduled report.
08-04-23
In this report, the apparatus completed initial assembly and began final assembly.
07-21-23
In this report, the cab continued initial assembly, the frame build continued, the pump house remained unavailable for photos, and the body continued through paint.
07-14-23
This week, the cab started initial assembly, the frame build began, the pump house was unavailable for photos, and the body continued the paint process.
06-30-23
In this report the cab completed paint and was staged, the pump house continued initial assembly, and the body began the paint process.
06-23-23
The cab completed paint and was staged, the pump house continued initial assembly, and the body began the paint process.
06-16-23
The cab continued the paint process, the pump house began initial assembly, and the body completed fabrication and was staged.
06-02-23
There will be no report this week due to the unit being unavailable for photos or no progress since the last report on the unit.
05-12-23
This new Pierce apparatus is now in production. In this report the cab began fabrication.