03-15-24
In this report, the apparatus completed testing and was released to quality and graphics where any remaining content will be
applied. Once finished, it will be made ready for final inspection. This is the last scheduled report.
03-08-24
In this report, the aerial device arrived, completed initial assembly, and was pinned to your apparatus followed by the start of aerial testing.
03-01-24
In this report, the apparatus completed final assembly and released to initial test.
02-16-24
In this report, the body completed initial assembly and was merged with the chassis followed by the start of final assembly.
02-09-24
In this report, the torque was being merged with the chassis while the body completed paint and began initial assembly.
02-02-24
In this report, the cab and pump house were installed on t the frame, the torque began initial assembly, and the body continued through paint.
01-26-24
In this report, the cab completed paint and began initial assembly, the frame build continued, the pump house continued initial assembly, the torque box remained staged, and the body began the paint process.
01-19-24
In this report, the cab continued through paint, the frame build continued, the pump house began initial assembly, the torque box remained staged (no photos), and the body completed fabrication and was staged.
01-12-24
In this report, the cab completed fabrication and began the paint process, the frame build began, the pump house structure remained staged, the torque box was staged, and the body began fabrication.
01-05-24
In this report, the cab continued fabrication while the pump house structure remained staged.
12-29-23
Your new Pierce apparatus is now in production! In this report, the cab began fabrication while the pump house structure was fabricated and staged.