08-16-24

In this report, the apparatus remained staged while the aerial device began initial assembly.


08-09-24

In this report, the apparatus remained staged while the aerial device arrived and was staged.


08-02-24

In this report, the apparatus remained staged for aerial pin.


07-26-24

In this report, the apparatus completed final assembly and was staged.


07-19-24

In this report, the apparatus continued final assembly in an offline area.


07-12-24

In this report, the front body module was installed while the apparatus completed initial assembly followed by the start of final assembly.


06-28-24

In this report, the torque box completed installation followed by the rear body module being merged with the chassis during the start of initial assembly, and the front body module completed initial assembly.


06-21-24

In this report, the torque box was installed on the chassis, the front body module was fabricated and painted, and the rear body module completed paint and was staged.


06-14-24

In this report, the chassis remained staged, the torque box remained staged, and the rear body module began the paint process.


06-07-24

In this report, the cab completed initial assembly and was installed on the frame followed by the pump completing initial assembly then merged with the chassis while the torque box remained staged, and the rear body module completed fabrication.


05-31-24

In this report, the cab began initial assembly, the frame build continued, the pump house structure was painted, the torque box was staged, and the rear body module began fabrication.


05-24-24

In this report, the cab completed paint and was staged while the frame build began.


05-17-24

In this report, the cab continued through paint.