PROGRESS UPDATES


10-25-24

In this report, final assembly continued.


10-18-24

In this report, the body was installed on the chassis followed by the start of final assembly.


10-11-24

In this report, the chassis continued assembly while the body completed initial assembly and was staged to be installed.


10-04-24

In this report, the chassis remained staged to continue assembly while the body completed the paint process.


09-27-24

In this report, the cab completed initial assembly and then was installed on the frame while the body completed fabrication and was staged.


09-20-24

In this report, the cab began initial assembly, the frame build continued, and the body began the fabrication process.


09-13-24

In this report, the cab completed the paint process while the frame build began.


09-06-24

In this report, the cab began the paint process.


08-31-24

In this report, the cab completed fabrication.


08-23-24

This new Pierce apparatus is now in production! In this report, the cab began fabrication.