07-19-24
In this report, the pump house was installed on the chassis followed by the body completing paint and initial assembly then being merged with the chassis.
07-12-24
In this report, the cab completed initial assembly and was installed on the frame, the pump house completed initial assembly and was staged, and the body began the paint process.
06-28-24
In this report, the cab completed paint and was staged, the frame build continued, the pump house continued initial assembly, and the body remained staged.
06-21-24
In this report, the cab continued through paint, the frame build continued, the pump house was painted, and the body completed fabrication and was staged.
06-14-24
In this report, the cab completed fabrication and began the paint process, the frame build began, the pump house began initial assembly, and the body began fabrication.
06-07-24
This new Pierce apparatus is now in production! In this report, the cab began fabrication.