39069 – Long Hill

Enforcer Rescue
Job #: 39069

PROGRESS UPDATES


09-20-24

In this report, the apparatus completed final assembly and began the quality and graphics process where any remining content will be applied.


09-13-24

In this report, the apparatus continued final assembly.


09-06-24

In this report, final assembly continued.


08-31-24

In this report, the body completed fabrication and was merged with the chassis followed by the start of final assembly.


08-16-24

In this report, the cab completed initial assembly and was installed on the frame while the body continued the fabrication process.


08-09-24

In this report, the cab began initial assembly, the frame build continued, and the body continued the fabrication process.


08-02-24

In this report, the cab completed paint and was staged, the frame build continued, and the body began fabrication.


07-26-24

In this report, the cab completed fabrication and began the paint process while the frame build began.


07-19-24

This new Pierce apparatus is now in production! In this report, the cab began fabrication.