04-11-25
In this report, the body completed initial assembly and was merged with the chassis.
04-04-25
In this report, the cab and pump house completed initial assembly and were merged with the frame while the body began initial assembly.
03-28-25
In this report, the cab continued initial assembly, the frame build continued, the pump house was painted, and the body completed fabrication and paint.
03-21-25
In this report, the cab completed paint and began initial assembly, the frame build began, the pump house continued initial assembly, and the body continued fabrication.
03-14-25
In this report, the cab began the paint process, the pump house began initial assembly, and the body began fabrication.
03-07-25
In this report, the cab completed fabrication and was staged while the pump house structure was fabricated.
02-21-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.