39163 – Little Silver

Enforcer Pumper
Job #: 39163

PROGRESS UPDATES


11-22-24

In this report, the apparatus continued the quality process.


11-01-24

In this report, the cab and pump house completed initial assembly and were installed on the frame followed by the body completing paint and initial assembly then merged with the chassis while initial apparatus assembly continued.


10-25-24

In this report, the cab continued initial assembly, the frame build continued, the pump house was painted, and the body completed fabrication and began the paint process.


10-18-24

In this report, the cab completed paint and began initial assembly, the frame build continued, the pump house began initial assembly, and the body began fabrication.


10-11-24

In this report, the cab continued through paint while the frame build began.


10-04-24

In this report, the cab began the paint process.


09-27-24

This new Pierce apparatus is now in production! In this report, the cab was fabricated and staged.