Bellmawr – 38421

Enforcer HDRP
Job #: 38421

PROGRESS UPDATES


05-10-24

In this report, the apparatus completed testing and was released to quality and graphics where any remaining content will be applied. Once finished it will be made ready for the customer acceptance inspection. This is the last scheduled report.


05-03-24

In this report, the apparatus completed final assembly and released to test.


04-26-24

In this report, the apparatus completed initial testing and began final assembly.


04-19-24

In this report, the apparatus completed initial assembly and released to initial test.


04-12-24

In this report, the pump house was merged with the chassis while the body completed the paint process and initial assembly. The body was then merged with the chassis during the start of initial assembly.


04-05-24

In this report, the chassis continued assembly, the pump house continued initial assembly, and the body began the paint process.


03-29-24

In this report, the cab was installed on the frame, the pump house began initial assembly, and the body was staged to begin the paint process.


03-22-24

In this report, the cab completed paint and began initial assembly, the pump house structure was fabricated, and the body completed fabrication and was staged.


03-15-24

In this report, the cab began the paint process while the body began fabrication.


03-08-24

In this report, the cab completed fabrication and was staged.