07-05-24
In this report, the apparatus was moving through quality
and graphics where any remaining content will be applied.
Once finished, it will be made ready for the customer
acceptance inspection. This is the last scheduled report.
06-28-24
In this report, the apparatus completed aerial testing and was released to quality and graphics.
06-21-24
In this report, the aerial device completed initial assembly and was pinned to the apparatus followed by the initial pump test completion and the start of aerial testing.
06-14-24
In this report, the apparatus remained staged while the aerial device arrived and began initial assembly.
05-10-24
In this report, the apparatus completed final assembly and was released for initial testing.
05-03-24
In this report, the front and rear body modules were merged with the chassis followed by the start of final assembly.
04-26-24
In this report, the torque box was merged with the chassis and staged to continue assembly, the front body module began initial assembly, and the rear body module completed initial assembly and was staged.
04-19-24
In this report, the pump house was installed on the chassis, the torque box began initial assembly, and the front and rear body modules completed paint and were staged.
04-12-24
In this report, the chassis was staged to continue assembly, the pump house continued initial assembly, the torque box remained staged, the front body module continued through paint, and the rear body module began the paint process.
04-05-24
In this report, the cab was installed on the frame, the pump house began initial assembly, the torque box was staged, the front body module began the paint process, and the rear body module remained staged.
03-29-24
This new Pierce apparatus is now in production! In this report, the cab began initial assembly, the frame build began, the front body module was fabricated, and the rear body module was fabricated and staged.